Report_Id: 229917 Est NO 0005 |
Date:12/29/2022 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 229917 | Estimate Number | 0005 | Estimate Type | PROGRESS | ||
District Office | PIKEVILLE (12360) Wright, Doug | ||||||
Contractor | FREDERICK & MAY CONSTRUCTION CO | ADDR SN 0 VC Code KY0036479 | |||||
PO BOX 337 | |||||||
WEST LIBERTY , KY , 41472 | |||||||
Pay Period | 11/19/2022 TO 12/02/2022 | ||||||
Date Approved | 12/06/2022 | ||||||
Primary Proj Number | BR06010742200 | ||||||
Project No. | EMERGENCY | ||||||
Primary County | KNOTT | ||||||
Name of Road | CR 1074 LEE GAYHEART DRIVE OVER WILEY BRANCH CREEK | ||||||
Description | REPLACE BRIDGE (060N00905N) ON LEE GAYHEART DRIVE (CR-1074) OVER WILEY BRANCH CREEK. | ||||||
Date Let | 08/01/2022 | Formal Acceptance | |||||
Date Awarded | 09/17/2022 | Date Work Began | 09/26/2022 | ||||
Date Contract Executed | 08/01/2022 | Open To Traffic | |||||
Date NTP Issued | 08/01/2022 | Actual Completion Date | 11/17/2022 | ||||
Current Contract Amount | $378,872.00 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $362,422.00 |
Total Earnings | $372,280.39 |
$362,880.39 |
$9,400.00 |
|
Percent Complete | 98.26 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $6,591.61 |
Gross Earnings | $372,280.39 |
$362,880.39 |
$9,400.00 |
|
Total Change Orders | $16,450.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $372,280.39 |
$362,880.39 |
$9,400.00 |
|||
Contract Id | 229917 | Change Order Summary |
County | KNOTT | ||||||
Estimate Nbr | 0005 | Project Number | EMERGENCY | |||||||
Contractor | FREDERICK & MAY CONSTRUCTION CO | Period | 11/19/2022 TO 12/02/2022 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
001 | Added item Rip Rap on tracking project | Approved | 10/31/2022 | $22,000.00 | 0.0 | |||||
002 | Add new item_Remove unused item on MA_GR | Approved | 11/30/2022 | $-5,550.00 | 0.0 | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 229917 | COMMONWEALTH OF KENTUCKY |
County | KNOTT | ||||||
Contract Type | BRRL BRIDGE REPLACEMENT | TRANSPORTATION CABINET |
Primary Project Number | BR06010742200 | ||||||
Estimate Nbr | 0005 | Period | 11/19/2022 TO 12/02/2022 | |||||||
Contractor | FREDERICK & MAY CONSTRUCTION CO | |||||||||
Project | BR06010742200 | Fed/State Project Number | EMERGENCY | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | BR06010742200 | Fed/State Project Number | EMERGENCY | Category | 0001 BRIDGE - 060N00905N | |||||||
0005 | DGA BASE | 00001 | TON | 58.00 | 58.000 | 105.930 | 105.930 | 48.00 | 5,084.64 | |||
0010 | ROADWAY EXCAVATION | 02200 | CUYD | 24.00 | 24.000 | 24.000 | 24.000 | 100.00 | 2,400.00 | |||
0015 | GRANULAR EMBANKMENT | 02223 | CUYD | 47.00 | 47.000 | 47.000 | 47.000 | 80.00 | 3,760.00 | |||
0020 | GUARDRAIL TERMINAL SECTION NO 1 | 02360 | EACH | 2.00 | 2.000 | 2.000 | 2.000 | 100.00 | 200.00 | |||
0025 | GUARDRAIL END TREATMENT TYPE 7 | 02371 | EACH | 2.00 | 2.000 | 2.000 | 2.000 | 2,000.00 | 4,000.00 | |||
0030 | TEMPORARY SIGNS | 02562 | SQFT | 64.00 | 64.000 | 0.000 | 0.000 | 23.00 | 0.00 | |||
0035 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 9,500.00 | 9,500.00 | |||
0040 | STAKING | 02726 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 7,500.00 | 7,500.00 | |||
0045 | FOUNDATION PREPARATION | 08003 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 30,000.00 | 30,000.00 | |||
0050 | CONCRETE-CLASS A 8.1 OR MORE | 08100 | CUYD | 155.60 | 155.600 | 155.600 | 155.600 | 1,350.00 | 210,060.00 | |||
0055 | STEEL REINFORCEMENT | 08150 | LB | 18,523.00 | 18,523.000 | 18,523.000 | 18,523.000 | 2.00 | 37,046.00 | |||
0060 | GUARDRAIL STEEL W BEAM-S FACE CR | 20060ES719 | LF | 130.00 | 130.000 | 148.750 | 148.750 | 45.00 | 6,693.75 | |||
0065 | EROSION CONTROL | 21415ND | LS | 1.00 | 1.000 | 0.300 | 0.700 | 1.000 | 6,500.00 | 1,950.00 | 6,500.00 | |
0070 | RAIL SYSTEM TYPE T631 | 24896ED | LF | 52.00 | 0.000 | 0.000 | 0.000 | 250.00 | 0.00 | |||
8000 | CYCLOPEAN STONE RIP RAP | 08019 | TON | 0.00 | 400.000 | 322.700 | 322.700 | 55.00 | 17,748.50 | |||
8001 | GUARDRAIL-STEEL W BEAM-S FACE BR With Plate Posts - Lee Gayheart | 08801 | LF | 0.00 | 25.000 | 25.000 | 0.000 | 25.000 | 298.00 | 7,450.00 | 7,450.00 | |
Project | BR06010742200 | Fed/State Project Number | EMERGENCY | Category | 0002 DEMOBILIZATION | |||||||
0075 | MOBILIZATION | 02568 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 23,000.00 | 23,000.00 | |||
0080 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.250 | 0.250 | 5,350.00 | 1,337.50 | |||
SUBTOT | $9,400.00 |
$372,280.39 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |